New report shows one-year-old Silvertown Tunnel cuts congestion and boosts bus use alongside improved air quality

New report shows one-year-old Silvertown Tunnel cuts congestion and boosts bus use alongside improved air quality: TfL Image - SL4 buses using the Silvertown Tunnel

PN - 215

  • Congestion has dropped significantly, with northbound peak journey times approaching the Blackwall Tunnel up to 58 per cent quicker in the morning and 47 per cent in the evening 
  • Nitrogen dioxide concentrations have decreased on average by 17 per cent compared with the year prior to Silvertown Tunnel opening 
  • 21 zero-emission buses per hour serving Blackwall and Silvertown tunnels have supported 290 per cent increase in cross-river bus journeys 

A new Transport for London (TfL) report shows that the Silvertown Tunnel - opened in April 2025 - has made journeys faster and more reliable, alongside sustainability benefits including a four-fold rise in cross-river bus journeys and a notable drop in nitrogen dioxide concentrations [1].  

Delivered on time and on budget, the 1.4km tunnel opened on 7 April last year, becoming the first new road Thames crossing east of London's Tower Bridge in 33 years. Connecting Silvertown to the Greenwich Peninsula in east London, the objectives of the scheme include boosting network performance and resilience while supporting economic and population growth, providing improved cross-river transport links and managing congestion in the area through road user charging.

Latest monitoring data from the first year of operation shows that the road network is more resilient and reliable, improving journeys for local businesses and essential freight. As well as providing a new cross-river route, the Silvertown Tunnel has reduced congestion in other areas, with quicker journeys through the Blackwall Tunnel at all times in both directions and a 23 per cent reduction in the number of over-height vehicle incidents at the Blackwall Tunnel.

For those travelling on the A102 northbound approach to the Blackwall Tunnel from Sun in the Sands, peak journey times have reduced by 58 per cent in the morning and 47 per cent in the evening. Weekday cross-river traffic using both tunnels remains lower than the pre-opening levels seen at just the Blackwall Tunnel with analysis of the wider road network showing overall stable traffic volumes on key corridors of the A2, A12 and A13.

Without the Silvertown Tunnel, it was predicted that air quality in the area would get worse alongside congestion – but monitoring reveals that nitrogen dioxide concentrations have decreased by 17 per cent on average compared with the year before the tunnel opened, helping Londoners breathe cleaner air. The nitrogen dioxide concentrations measured in the year since the tunnel opened were significantly below thresholds set by the UK Air Quality Strategy, with the highest average concentration being 26.3 µg/m3 – well under the annual limit of 40 µg/m3.

New double-deck, zero-emission buses are making use of the dedicated bus and HGV lane through the Silvertown Tunnel. More than 30,000 journeys are being made each day across the new SL4 and extended 129 routes through the new tunnel as well as the existing 108 service through the Blackwall Tunnel. It is estimated that around a third of these journeys cross the river through the two tunnels - up 290 per cent on the year before - meaning more than one in ten (11 per cent) cross-river trips through the two tunnels are made by public transport. The route 108 has also become more reliable, with shorter waits and journey times [2]. These bus routes complement the free cycle shuttle service between North Greenwich and Royal Docks, which sees an average weekday demand of around 100-130 cyclists, supporting London’s cycling boom and encouraging sustainable travel across the capital.

TfL Image - 129 bus using the Silvertown Tunnel

All journeys on bus routes through the Silvertown and Blackwall Tunnels were free until 26 May 2026, with more than 10 million journeys making use of the free travel offer on the Silvertown Tunnel bus network in its first year. Cross-river trips on the Docklands Light Railway (DLR) were also made free, with an average of 5,025 DLR free trips each week and more than 260,000 over the year.

To manage traffic demand, minimise environmental impacts and ensure the new tunnel achieved its objectives, TfL was required to introduce user charges for both the Blackwall and Silvertown Tunnels, which analysis shows have been working successfully [3]. Tunnel charges will increase in line with inflation from 21 September 2026 while existing discounts for eligible residents, businesses and Blue Badge holders will remain in place.

Mayor of London, Sadiq Khan, said: “This analysis shows that the Silvertown Tunnel is proving a success, not only cutting journey times but encouraging more sustainable transport so we can keep cleaning up our air. I’m particularly pleased to see major reductions in congestion at the Blackwall Tunnel benefitting businesses and local residents. The Silvertown Tunnel is already transforming travel across the Thames as we continue building a greener, fairer, better London for everyone.”

Alex Williams, Chief Customer and Strategy Officer at TfL, said: “It’s excellent to see that the Silvertown Tunnel is successfully achieving what it set out to do – improving the resilience of the road network and reducing congestion, with air quality improving. By making it easier to travel by bus across and near the river, we’re also seeing a surge in customers choosing to travel more sustainably. With more reliable journeys, improved access to public transport and reduced emissions, the tunnel is delivering real benefits for people and businesses on both sides of the river." 

Edward Richardson, BusinessLDN’s Transport Programme Director, said: “It’s great to see that the Silvertown Tunnel is helping to reduce congestion, improve air quality and boost cross-river connectivity in the area. This highlights the important role that partnership between the public and private sectors has to play in delivering the infrastructure that Londoners and businesses across the capital need.”

Contact Information

TfL Press Office
Transport for London
0343 222 4141
pressoffice@tfl.gov.uk

Notes to editors

  • [1] The Silvertown and Blackwall Tunnels: Twelve-month monitoring report can be found here: Silvertown & Blackwall Tunnels Monitoring Report
  • [2] Londoners who use the route 108 bus between Stratford International and Lewisham via the Blackwall Tunnel are experiencing around 28 per cent less excess waiting time – the average time passengers wait beyond the scheduled wait time – compared to the period before the Silvertown Tunnel opened
  • [3] As part of the scheme, the Development Consent Order stipulated TfL was required to carry out a 12-month review of the tunnel user charges. This was to ensure they were having the intended effect of managing traffic demand, which then enables wider objectives like improving the road network’s performance and resilience, encouraging use of cross-river public transport links, and supporting economic growth. The review concluded that the user charges were working as expected, with traffic conditions consistent with what was anticipated
  • Compliance with the user charge continues to be high at around 90 per cent and the number of penalty charge notices issued has steadily decreased over the first year of operations
  • To help support local residents and businesses to cross the river via public transport and embed sustainable travel behaviour in the long term, free trips were offered on cross-river buses and refunded cross-river DLR trips until 26 May 2026, extending the original offer by seven weeks. Across the first twelve months of the new tunnel operating, there were more than 10 million free bus journeys undertaken and more than 260,000 DLR trips refunded
  • While the primary purpose of the tunnel user charges is to manage traffic demand for the river crossings and allow the project’s objectives to be achieved, the charges also provide a means of helping to repay the costs of the Silvertown Tunnel’s construction, operation and maintenance. Therefore, any revenue generated from the tunnel user charges is used for the operation, maintenance, and repayment costs for the tunnels with any surplus reinvested back into the wider public transport network. The implementation of a user charge is a requirement of the Development Consent Order for the Silvertown Tunnel, made by the Secretary of State for Transport in 2018
  • To calculate the new charges, TfL has used indexation based on the cumulative change in RPI between December 2024 (when the Board approved the initial user charges) and March 2026
  • The charge levels have been rounded to the nearest 5 pence increment (up or down). This means that, while the inflationary increase based on the change in RPI is 4.9 per cent, in practice most of the changes to user charges increase by less than this because of rounding (the effective overall rate being 4.4 per cent)
  • In line with the Development Consent Order, which granted TfL permission to construct the Silvertown Tunnel, TfL consulted with the Silvertown Tunnel Implementation Group (STIG) on the changes to the user charge levels
  • There are no changes at this time to the associated Penalty Charge Notices or registration fees
  • There are also no changes at this time to discounts and exemptions. The low-income residents’ discount will remain as a 50 per cent reduction on the new user charges and the business discount will continue as a £1 discount on the new off-peak user charges
  • Discounts and exemptions are available for certain eligible people and vehicles, including low-income residents (until at least April 2028) and local businesses. Drivers can sign up to TfL Auto Pay at tfl.gov.uk/auto-pay. More than 3.7 million vehicles are now signed up for TfL Auto Pay, up from around 2.65 million in January 2025. More than 80 per cent of tunnel user charges are now paid via Auto Pay
  • A table of the current and new charges is as below:

Silvertown and Blackwall User Charges – 6am to 10pm

 

Charges paid via Auto Pay

Charges paid via other channels

 

 

Standard off-peak charges

 

 

Peak charges

 

At all times

Motorcycle, moped, motor tricycle

£1.50 will become £1.55

£2.50 will become £2.60

£2.50 will become £2.60

Car and small van

£1.50 will become £1.55

£4.00 will become £4.20

£4.00 will become £4.20

Large van

£2.50 will become £2.60

£6.50 will become £6.80

£6.50 will become £6.80

Heavy Goods Vehicles

£5.00 will become £5.25

£10.00 will become £10.50

£10.00 will become £10.50

Auto Pay Peak Charges: Mon-Fri only, Northbound 6am - 10am, Southbound 4pm - 7pm

Penalty Charge Notice for non-payment - £180 (Reduced to £90 if paid within two weeks; maximum one PCN per day)

  • Alongside the construction of the Silvertown Tunnel, TfL has carried out a comprehensive programme of monitoring since 2020 and has regularly published baseline reports and monitoring data which helps TfL’s understanding of local air quality, traffic levels and socioeconomic impacts. This monitoring will continue until at least April 2028 (three years after the tunnel has opened) with TfL continuing to publish reports during this period showing how they are meeting their obligations, or if further changes need to be made. Post-opening data on air quality and noise is also reviewed annually by an independent expert
  • There have been regular meetings with the Silvertown Tunnel Implementation Group throughout the construction of the Silvertown Tunnel, which will continue for the duration of the monitoring period. Papers and meeting minutes are available at tfl.gov.uk/travel-information/improvements-and-projects/silvertown-tunnel-implementation-group